One more question to add to pricing, backup and lock-in: whose 400 MW is it? If it’s existing Chiba output rather than new units, it comes out of supply for the region with the longest connection waits. The US tested this first. In November 2024, FERC blocked a bid to raise Amazon’s directly connected load at Talen’s Susquehanna plant from 300 to 480 MW, after utilities argued it put the data center ahead of the grid. The deal came back in 2025 as a grid supply agreement. Nobody has said yet which kind Chiba is.
Good point. The public announcements confirm up to 400 MW at Chiba, but they do not say whether that capacity comes from existing generation or requires additional units.
That is still unclear, and it will be important to see how JERA plans to supply that capacity as the project develops. The Susquehanna example is a useful comparison.
Siting at the plant fence makes sense against that backdrop: DC Hub's power index has Tokyo at a composite 15.2, in the AVOID band for new grid power (a modeled read calibrated from TEPCO and OCCTO disclosures, so directional rather than live telemetry). Behind-the-meter at Chiba sidesteps the 5 to 10 year connection wait, but it moves the risk onto the fuel contract, which is why your pass-through vs fixed-price question is the one I'd want answered before an anchor tenant signs. A 15 to 25 year contract indexed to LNG would look very different after another Hormuz-style spike. (DC Hub (dchub.cloud), as of Oct 22, 2026)
Agreed. The fuel contract is one of the biggest unresolved pieces.
The project solves the connection-time problem, but the economics look very different depending on whether LNG costs are passed through or fixed. Over a 15-to-25-year contract, that pricing structure could matter as much as the speed advantage at the start.
One more question to add to pricing, backup and lock-in: whose 400 MW is it? If it’s existing Chiba output rather than new units, it comes out of supply for the region with the longest connection waits. The US tested this first. In November 2024, FERC blocked a bid to raise Amazon’s directly connected load at Talen’s Susquehanna plant from 300 to 480 MW, after utilities argued it put the data center ahead of the grid. The deal came back in 2025 as a grid supply agreement. Nobody has said yet which kind Chiba is.
Good point. The public announcements confirm up to 400 MW at Chiba, but they do not say whether that capacity comes from existing generation or requires additional units.
That is still unclear, and it will be important to see how JERA plans to supply that capacity as the project develops. The Susquehanna example is a useful comparison.
Siting at the plant fence makes sense against that backdrop: DC Hub's power index has Tokyo at a composite 15.2, in the AVOID band for new grid power (a modeled read calibrated from TEPCO and OCCTO disclosures, so directional rather than live telemetry). Behind-the-meter at Chiba sidesteps the 5 to 10 year connection wait, but it moves the risk onto the fuel contract, which is why your pass-through vs fixed-price question is the one I'd want answered before an anchor tenant signs. A 15 to 25 year contract indexed to LNG would look very different after another Hormuz-style spike. (DC Hub (dchub.cloud), as of Oct 22, 2026)
Agreed. The fuel contract is one of the biggest unresolved pieces.
The project solves the connection-time problem, but the economics look very different depending on whether LNG costs are passed through or fixed. Over a 15-to-25-year contract, that pricing structure could matter as much as the speed advantage at the start.